Keyword      Search in       

Contact
Imprint
Privacy Policy
Site Map

RSS Feed News. Your shopping cart.

Google gadget.

 

Discussion Forum

 

RE: Validation Master Plan

Contribution from Siegfried Schmitt written on 4/15/2002 at 12:37

Original contribution: Validation Master Plan written by H. Martin on 3/21/2002 at 09:40)

The VMP and the schedule are living documents and this should be referenced as such in the VMP. It is good practice to detail activities by week or at least by month. Regular reviews allow updates to the schedule.

Answers to this contribution:

Answering this Contribution:

    

Name:

E-mail:

re. / topic:

Contribution: